Budget Category F5 "Allocated IDC Base"

  • 1.  Budget Category F5 "Allocated IDC Base"

    Posted 07-15-2022 10:55
      |   view attached
    Hello,

    In Cayuse under the RR Budget tab, sub-tab 3, Budget Category F.5... for "Allocated IDC Base", is this the amount that the primary institution is assessing IDC on?
    For example, if we assess IDC on the first $25K of the subaward, then it would be entered as "$25,000" for the first year only, and $0 in subsequent years, correct?
    Thank you for the clarification.

    Linda



    ------------------------------
    Linda Phi-Nguyen
    Research Analyst